Current Projects

Waterford Gas Network Reinforecement Project

Bord Gáis Networks is upgrading the natural gas network in areas of Waterford City which is essential to reinforce the supply of natural gas to the city and facilitate future extension of the network.

Phase 1

Between June and September 2010, the pipeline works will be carried out in the following areas:

  • Otteran Place
  • Water Street
  • Lower Newtown Road 
  • Newtown Road 

Click here to view a map of the Phase 1 pipeline route

Click here to download the Phase 1 project leaflet

Phase 2

Between July 2010 to December 2010, the pipeline works will be carried out in the following areas:

  • Ballytruckle Road
  • Inner Ring Road 
  • South Parade

Click here to view a map of the Phase 2 pipeline route

Click here to download the Phase 2 project leaflet 

Construction

The reinforcement works will involve trench excavation and the laying of natural gas pipelines on the above streets.  All excavations will be backfilled and all surfaces will be restored. The work will be carried out by contractors GMC and CLG on behalf of Bord Gáis Networks.

Every effort will be made to keep disruption to a minimum during construction. Local traffic management plans will be put in place on the affected routes. Where necessary all temporary road closures and traffic diversions will be advertised in local newspapers in advance. 

Contact Information

If you have any queries on any aspect of the pipeline works please contact:

Phone: 051 302509 (9.00am – 5.00pm)